The short answer
A failed hydrostatic test means the new water main is not accepted. The pressure dropped, the water loss was over the allowance, or there is a visible leak at a joint, valve or hydrant. The main stays off the live network. It is connected only after a passing test.
How the test works
A new water main is isolated and filled with potable water. Trapped air is bled off at the high points, air valves and hydrants. Air left in the line compresses under pressure and moves the gauge even when the pipe is tight, so a reading taken with air still in the main cannot be trusted.
Water is then pumped in to the test pressure. That pressure is usually 1.5 times the working pressure, or the figure in the Sydney Water or council specification. It is held for the specified time, usually 4 hours. Any drop is measured by the volume of water added to restore the pressure. Joints, valves, hydrants and air valves are checked for weeping during the hold.
The pressure, the hold and the allowable loss come from the specification. In the Sydney Water area the method is WSA 03-2011-3.1 (Sydney Water Edition 2014). The NATA accredited report records the pressure, the hold, the makeup volume and the result.
When it’s required
Hydrostatic testing is the acceptance test for new pressure pipelines: drinking water mains, fire mains and pressure sewer rising mains. Sydney Water requires it on developer water mains before a Section 73 Compliance Certificate, and before the new main is connected to a live main. Hunter Water, Central Coast Council, Shoalhaven Water and other NSW authorities require the same class of test on new pressure mains in their areas.
How to prepare the site
The section has to be finished before the tester arrives. Pipe laid and jointed, flanges and mechanical joints torqued, gaskets seated, and every branch capped or valved so the length can be isolated. Thrust blocks and anchors need to be in place and cured, so they cannot move once the pressure comes on.
Air valves, scours, hydrants and temporary outlets should be installed, and someone on site needs to know which are open and which are shut. One tap or valve left open will fail a four-hour hold, and so will a gland that was never tightened.
Filling needs a water source big enough to fill the section slowly, so air leaves as the water rises, and a place to discharge the test water. The test point needs vehicle access, and a marked-up plan with the section limits, valve numbers and hydrants.
How long it takes and what affects it
The hold is usually 4 hours, and the visit is longer than the hold. Filling, bleeding air and raising the pressure can take as long as the test itself, and longer on a large diameter, a long section, or a main with several high points.
A weep at a flange can be found on the first walk. A pressure loss with no wet spot means closing valves and testing the lengths between them until the loss sits in one length. How long that takes depends on the length of the main, how many valves can split it, and whether the fittings are still open. A backfilled main can turn one failed hold into a return visit.
Air trapped at a high point will also drop the gauge. A thrust block that shifts during the hold can open a joint that was tight at the start.
Results
A pass is a hold at the specified pressure for the specified time, makeup water inside the allowance, and no visible leak at joints, valves or hydrants. The NATA accredited report records the test pressure, the duration, the makeup volume and the pass.
A fail is a pressure drop, makeup water over the allowance, or a visible leak. Any one of them is a fail. A gauge that will not settle because air is still in the line stays a fail until the air is removed and the hold is repeated. The acceptance package needs the passing retest.
The main stays disconnected from the live network until it passes.